PROJECT RESPONSIBILITIES & HANDOVERS

Furniture Sourcing Responsibility Matrix

Connect each sourcing task to the people, approvals and records it needs. Agree the handovers before your furniture order moves forward.

Furniture selection and final-review reference
PROJECT RESPONSIBILITY MATRIX

Furniture Sourcing Tasks & Responsibilities by Project Stage

Confirm who prepares, who approves and which record moves the order to the next stage. The roles below are a planning baseline, not a replacement for your agreed scope.

10 responsibilities5 project parties4 project stages
10 responsibilities
TaskClient / approverDesignerArcaya / sourcingSupplier / factoryLogistics / receivingHandover record
Budget and prioritiesApproveAdviseCoordinateAdvise-Approved project brief
Site dimensionsProvide / approveConfirm if appointedReview supplied dataUse approved data-Verified dimensions
Furniture specificationsApprovePrepare if appointedCoordinateConfirm feasibility-Signed specification revision
Samples and finishesApproveReview if appointedCoordinateProvide agreed samples-Sample approval record
Quotation and scopeApproveReview if appointedPrepare agreed scopeConfirm product costsQuote agreed logisticsApproved quotation
Production updatesResolve decisionsSupport if appointedFollow up if includedProduce / report progress-Milestone update
Pre-shipment checksReview reportSupport if appointedCheck if includedAddress agreed defects-Inspection / issue record
Packing and item labelsConfirm receiving needs-Coordinate if includedPack to agreed scopeConfirm handling needsPacking list
Freight and import arrangementsApprove / appoint parties-Coordinate if includedProvide agreed documentsExecute contracted scopeShipping / broker records
Receiving and installationAppoint receiving teamSupport if appointedSupport if includedProvide agreed instructionsDeliver contracted scopeReceiving / defect record
Approve · Authorized written decisionCoordinate · Connect the parties and recordsIf included · Confirm in the agreed scope

Planning template only. The actual project agreement determines responsibilities, included services and liability. Appoint qualified parties for site measurements, specialist testing, import requirements and installation where needed.

CLIENT, DESIGNER, AGENT, SUPPLIER & LOGISTICS

Client, Designer, Agent, Supplier & Logistics Roles

A role is not a blanket promise. Confirm the appointed parties, decision authority and included work for your actual project.

Upholstered bed frame with exposed wooden slats01 / CLIENT & APPROVER

Client: Approve Quantities, Budget & Final Selections

Confirm priorities, quantities, room needs and the approved budget. Name one authorized approver or record exactly which person can approve each part of the order.

Two timber-tone finish panels displayed side by side02 / DESIGNER, IF APPOINTED

Designer: Review Layouts, Specifications & Finishes

Prepare or review the product schedule, proportions and finish references. Agree whether the designer checks site measurements, reviews technical details or only advises on selection.

Open cabinet with separate compartments for item-level responsibility checks03 / ARCAYA & SOURCING

Sourcing Agent: Coordinate Quotes, Checks & Records

Coordinate the agreed sourcing work, quotations and decision records. Confirm which production updates, inspections and packing checks are included; keep extra work visible before approval.

Furniture components and workstations inside a workshop04 / SUPPLIER & FACTORY

Supplier: Confirm Specifications, Produce & Resolve Defects

Confirm feasibility and the product specification. Provide agreed samples and progress information, identify changes and address issues within the agreed order scope.

Workers loading wood-crated furniture into a shipping container with a forklift05 / LOGISTICS & RECEIVING

Logistics: Confirm Pickup, Delivery & Handling Scope

Record the collection and delivery endpoints, package information and contracted handling. Appoint the broker, local receiving and installation parties where needed.

No designer appointed? Assign the design and specification decisions explicitly. A task still needs an owner.

Plan the furniture purchase
DECISION POINTS

Approval Owners for Specifications, Samples & Changes

A person should own each final decision. Keep specifications, samples and quotations attached to the approved revision.

01

Dimensions, Materials & Quantity Approval

Confirm sizes, materials and quantities before ordering.

02

Finish & Product Sample Approval

Record the finish or sample reference used for approval.

03

Substitution, Price & Schedule Approval

Approve substitutions and revised costs before work proceeds.

04

Inspection Scope & Receiving Responsibilities

Confirm inspection scope and who receives the goods.

Curved wood component during furniture production
Structure & dimensionsApprove the actual construction and measured components, not only an attractive reference image.
Physical decorative finish sample beside additional reference cards
Materials & finish codesKeep the physical reference, sample code and written approval connected to the current item schedule.
Three round wooden tables with different heights and sizes
Configuration & changesRecord sizes, heights and the complete set. A substitution needs a clear approval and a revised cost or date where applicable.
Approval & Evidence

Responsibilities for Missing Details, Failed Samples & Delivery Issues

A role matrix explains the normal workflow. A separate decision record keeps missing information, failed samples and delivery issues from becoming an unowned task. Appoint the people below for your project; these are proposed roles, not automatic service commitments.

ExceptionProposed owner and responseRelease record
Site measurement is missingClient appoints the site measurer; designer checks interfaces if retained. Hold the affected item.Verified dimensions, drawing revision and named approver.
Sample does not match the agreed referenceSupplier identifies the mismatch; sourcing contact coordinates options; client approves the resolution.Revised sample or documented concession, with cost and date effect.
Supplier proposes a substitutionSupplier identifies the changed component; designer reviews if retained; client authorises or rejects it.Old/new specification, price effect, lead-time effect and written decision.
A batch has unresolved inspection issuesSupplier supplies correction evidence; appointed checker reviews the agreed scope; release approver decides.Issue log, recheck evidence and explicit hold or release.
Destination delivery or installation is not readyClient-appointed receiving team confirms access and readiness; logistics party revises its contracted plan.Receiving appointment, storage arrangement and agreed extra costs.
Damage is found at receivingReceiving team records package and item condition; agreed claim contact coordinates next steps.Item code, package ID, photographs, dates and proposed remedy.

For every exception, keep the decision owner separate from the person collecting information. An unresolved item should remain on hold rather than be treated as approved by silence.

PRODUCTION & PACKING RECORDS

Production, Packing & Handling Evidence by Item

A progress photo is useful when you can connect it to the correct item, approved revision and next decision. Generic workshop or warehouse images are not an inspection report.

Round table components ready for a production-stage review
Production & issue recordIdentify the item, production stage and open issues. State who follows up and what evidence closes the issue.
Furniture cartons on timber pallets with product-thumbnail labels and handling pictograms
Package identificationMatch package numbers and product labels to the packing list. Keep quantities and the collection or handover record together.
Upholstered seating protected with wrapping and timber supports
Protection & handling scopeRecord the agreed protection for the actual item, including vulnerable finishes, corners and removable parts.

Website workflow references show the type of activity. They are not evidence that any particular order has been inspected or approved.

PROJECT HANDOVER REGISTER

Task Approvals, Open Issues & Handover Records

Use the approved specification and sample revision, record the decision-maker, and keep unresolved questions visible before the next agreed milestone.

  • Approval. An authorized name, date and specification revision.
  • Open issues. The item, issue owner, proposed action and target date.
  • Handover. What was passed to whom, and the supporting record.
  • Closure. The agreed outcome and who confirmed it.
PROJECT DETAILS

Project Contacts & Handover Register

Planning worksheet only. The project agreement determines the appointed parties, responsibilities and included services.

Furniture unloading and receiving at destination
Packaged goods at a destination unloading handover.
DESTINATION RESPONSIBILITIES

Unloading, Carry-In, Assembly & Installation Responsibilities

Delivery, unloading, carrying upstairs, assembly and installation are different tasks. Keep their owners and scope visible before dispatch.

  • Site access. Confirm doors, stairs, lift capacity, vehicle access and the receiving appointment.
  • Receiving team. Name the contact who counts packages and records visible condition.
  • Local work. Specify unloading, carry-in, assembly, installation and packaging removal where needed.
  • Problem reporting. Keep package labels and photos, and follow the agreed reporting and remedy process.

A sourcing coordinator does not automatically take on specialist testing, import compliance or local installation responsibilities. Appoint the appropriate qualified parties for the project.

Confirm my delivery scope
BEFORE YOU START

Furniture Sourcing Responsibility Matrix FAQs

Clear decisions before a confirmed order.

Is this a contract?

No. This is a planning template. Responsibilities, liability and included services are governed by your project agreement and any relevant supplier and logistics agreements.

Who approves the final product specifications?

The authorized project approver should confirm the specifications in writing. Identify that person before orders are placed.

What if a designer is not involved?

Assign design and specification decisions to the client or another explicitly appointed party. Do not leave an approval step without an owner.

Does a quality check guarantee compliance?

No. Define the check scope and any required independent tests or documentation separately. A visual inspection is not a substitute for all project or destination requirements.

Who approves a substitution or a changed finish?

The authorized approver should confirm the specific change in writing. Connect that approval to the revised item schedule, sample reference and any agreed change in price or timing.

Does door-to-door delivery include assembly or installation?

Not automatically. Confirm the delivery endpoint and separately agree unloading, carrying into the room, assembly, installation and packaging removal where needed.

What should be recorded when an issue is still open?

Record the item code, current revision, issue evidence, responsible contact, proposed action and target date. Keep the issue visible until the agreed outcome is confirmed by the appropriate decision-maker.

Who approves a supplier substitution?

Name one authorised approval owner in the project records. The supplier should describe the old and proposed specification plus price and date effects. A coordinator collecting information does not automatically have authority to approve the change.

What happens when a required approval is late?

Record the missing decision, its owner and the affected milestone. Agree whether only that item or the relevant batch is held, then update the schedule. Do not treat no reply as approval.

Furniture Sourcing Enquiry

Discuss Your Furniture
Sourcing Responsibilities

Send your product list, reference images or room plans. We’ll review your project and show you the clearest path to an accurate quotation.

  • Product Lists, Reference Images & Room PlansA product list, reference images or room plans are enough for us to begin.
  • Project Scope & Quotation RequirementsWe identify missing details, confirm the scope and explain the next steps before you commit.
  • Supplier, Quality Check & Shipping CoordinationYour Arcaya contact coordinates suppliers, specifications, quality checks and shipping.
Reply in 1-2 working daysNo payment at this step

Furniture Sourcing Enquiry

4 quick fields

Service type is set to Furniture Sourcing—everything below the line is optional.

What do you have so far?
Add details & files (optional)

Budget, timing, product list or plans—skip if you’re not sure yet.

Submitting starts a conversation—not an order. No payment at this step.