What Dates Should You Give Your Furniture Sourcing Agent?
Your studio has set the client review, and the site team knows when furniture needs to arrive and be installed. Share those dates in your first request for pricing. We’ll check which pieces have enough time for samples and approvals, and where it makes sense to have a backup ready.

Give Us the Installation Deadline
Tell us what’s driving the installation date, whether it’s a photo shoot, opening, or move-in. Flag rooms that can be installed later so we can check whether splitting the delivery would help.
Confirm When the Site Can Receive Furniture
Ask the site or warehouse team when they can take delivery. Allow separate time for booking, unpacking, inspection, and installation. We’ll confirm which steps are included in each supplier’s scope.

Put Client Approvals on the Supplier’s Calendar
Your studio may be able to review drawings on the 15th even though your client can’t approve samples until the 22nd. Give us both dates so the supplier can tell us when production could start.
Allow Time for Samples to Reach Your Studio
Tell us when you need samples in hand and when you can give feedback. We’ll check what’s ready to ship, what needs to be made, and how much time to allow if you need a second round.

Flag Site Measurements and Drawings That Could Hold Up an Order
List when the site team will take final measurements, when your studio will issue its drawings, and when the maker’s shop drawings can be reviewed. If a cabinet depends on finished walls, we can check which finishes and details the maker can confirm in the meantime.
Ask When the Production Lead Time Starts and Ends
Check whether the clock starts when the supplier receives the deposit, approves the drawings, or gets the specified fabric. Then ask whether the quoted end date means the piece is built, ready to inspect, or ready to ship.

Work Backward from the Installation Date
Start with the last day the site can take delivery and work backward through local delivery, inspection on arrival, freight, and checks before shipping. In one shipment from Foshan to Toronto, the buyer tracked factory completion, vessel departure, and home delivery as separate dates.
Rule Out Versions That Won’t Arrive in Time
Check the exact finish, orientation, and quantity. A sofa in a stock fabric might make the date while the specified upholstery takes longer. Your studio can review another fabric or put the backup in front of the client.

Set a Deadline for Switching to the Backup
Tell us the latest you can switch pieces and still make the presentation and installation dates. If the first choice is still uncertain, we’ll have the backup’s photos, dimensions, and availability ready for your review.
A Date Checklist for Your First Quote Request
One supplier needs fabric approval by May 18. Another can wait until May 22. If May 22 is the earliest your client can review samples, ask us to confirm the second supplier’s schedule first.
| Milestone | Example date or status | Who confirms |
|---|---|---|
| Installation complete | June 30 | Site lead |
| Furniture received on site | By June 24 | Receiver and delivery team |
| Inspection, freight and delivery | To confirm for each candidate | Maker, freight forwarder and delivery team |
| Sample approval | May 22 | Design studio |
| Selection approved | May 15 | Design studio and client |